“Critical decision” keeps Versatile Test Reactor on target
Now that the Department of Energy has approved Critical Decision 1 for the Versatile Test Reactor (VTR) project, the engineering design phase can begin once Congress appropriates funding, according to a September 23 announcement from the DOE’s Office of Nuclear Energy. The DOE has requested $295 million for the project in fiscal year 2021.
The news came nearly one month after a team led by Bechtel National Inc. (BNI), and including GE Hitachi Nuclear Energy (GEH) and TerraPower, entered into contract negotiations with Battelle Energy Alliance (BEA) for the design-and-build phase of the VTR. GEH’s sodium-cooled fast reactor PRISM technology was selected to support the VTR program in November 2018.