Proposals being accepted for $21 billion Savannah River contract
The Department of Energy’s Office of Environmental Management (EM) has begun accepting bids on a new 10-year, $21-billion contract for the Savannah River Site in South Carolina. EM issued a final request for proposal for the SRS integrated mission completion contract (IMCC) on October 1, posting it to EM’s dedicated SRS IMCC website.
The IMCC would coalesce the work of two current contractors, including Savannah River Remediation, the site’s liquid waste contractor led by Amentum with partners Bechtel National, Jacobs, and BWX Technologies, into a single contract, combining liquid waste work with nuclear materials management.
The deadline for proposals for the site contract is December 1.