Major milestone reached at Vogtle-3

October 21, 2020, 9:30AMNuclear News

Vogtle-3, in September. Photo: Georgia Power

Georgia Power has announced the completion of cold hydro testing at Vogtle-3, one of two 1,100-MWe Westinghouse AP1000 pressurized water reactors under construction at the Vogtle site near Waynesboro, Ga.

Unit 3 construction is now approximately 94 percent complete, and the total Vogtle-3 and -4 expansion project is about 88 percent complete, according to the company’s October 19 announcement. The last major test for Vogtle-3 before initial fuel loading is hot functional testing.

Cold hydro testing of Unit 3 confirmed that the reactor’s coolant system functions as designed and verified that the welds, joints, pipes, and other components of the coolant system and associated high-pressure systems do not leak when under pressure, Georgia Power said. The company also noted that it expects to meet the regulatory-approved in-service dates for the new reactors: November 2021 for Unit 3, and November 2022 for Unit 4.

To continue reading, log in or create a free account!

Related Articles

Vogtle-4 enters commercial operation

April 29, 2024, 9:32AMNuclear News

Unit 4 at Georgia Power’s Plant Vogtle has entered commercial operation, the company announced today. The new unit can produce enough electricity to power an estimated 500,000 homes and...

“Buy the best and only cry once”

March 14, 2024, 9:30AMNuclear News

Spoiler alert: America has one more nuclear reactor on line.It’s been a long, hard slog for the Vogtle reactor expansion project, and the news coverage has been tough. I would describe it as...