Final outage completed at Palisades plant
Entergy Corporation’s Palisades nuclear power plant returned to service on October 21, following the completion of the Covert, Mich., facility’s final refueling and maintenance outage, which began on August 30.
The company invested more than $86.5 million during the outage, according to Entergy. The plant’s 600 full-time nuclear professionals worked with approximately 800 supplemental workers to replace reactor fuel and to inspect and upgrade hundreds of pipes, pumps, electrical components, and other equipment.