NextEra sets Duane Arnold D&D at $1 billion
NextEra Energy is estimating that it will cost just over $1 billion to decommission its Duane Arnold Energy Center over a period of 60 years, including spent fuel management and site restoration costs, according to a post-shutdown decommissioning activities report (PSDAR) and a decommissioning cost estimate the company submitted to the Nuclear Regulatory Commission in April. The NRC, with publication in the June 19 Federal Register, is requesting comments on the Duane Arnold PSDAR until October 19.