Centrus Energy expects first HALEU production in October
Centrus Energy announced on September 6 that it is conducting final system tests and expects to begin producing high-assay low-enriched uranium (HALEU) in October from its 16-machine gaseous centrifuge enrichment demonstration cascade at the American Centrifuge Plant in Piketon, Ohio. After achieving initial HALEU production, Centrus has specific goals to meet under contract as the company ramps the demonstration cascade to its target annual production rate of 900 kg per year.
Centrus is required under a cost-share contract with the Department of Energy to produce 20 kg of 19.75 percent–enriched HALEU in uranium hexafluoride (UF6) form by the end of this year. That contract, announced in November 2022, replaced an earlier contract signed in October 2019 that called for first production of HALEU by June 2022. The current contract calls for production at an annual rate of 900 kg of HALEU UF6 per year in 2024, with additional options—subject to appropriations—to produce material in future years.