China’s 51st power reactor enters operation

August 4, 2021, 12:01PMNuclear News
Workers in the control room of the newly operational Honghanye-5 reactor. (Photo: Liaoning Hongyanhe Nuclear Power Company)

China continues its relentless march toward the top of the list of nations with the most power reactors. On July 31, China General Nuclear Power Group (CGN) announced that Unit 5 at the Hongyanhe plant in Liaoning Province has begun commercial operation, giving China 51 commercial-scale power reactors, only five fewer than France, which currently sits at the number-two spot on the list with 56 operating reactors.

China’s Tianwan-6 up and running

June 11, 2021, 12:59PMNuclear News
The Tianwan-6 control room. Photo: CNNC

Unit 6 at the Tianwan nuclear plant has entered commercial operation, China National Nuclear Corporation announced last week. The domestically designed ACPR-1000 pressurized water reactor becomes CNNC’s 24th unit to enter service, raising the company’s installed generating capacity to 22.5 GWe (gross).

Tianwan-5 ready for commercial operation

September 11, 2020, 9:29AMNuclear News

Unit 5 at the Tianwan nuclear plant. Photo: CNNC

Unit 5 at the Tianwan nuclear power plant completed its full-power continuous operation assessment on September 8, meeting the conditions for commercial operation, China National Nuclear Corporation reported. The domestically designed ACPR-1000 pressurized water reactor will become CNNC’s 22nd reactor to provide power to China’s electric grid, raising the CNNC fleet’s installed capacity from 19.112 million kilowatts to 20.230 million, according to the company.

Tianwan-5 construction officially commenced on December 27, 2015, with the pouring of safety-related concrete. China’s National Nuclear Safety Administration issued a 40-year operating license for the unit on July 7 of this year, and two days later CNNC announced that first fuel loading had been completed. The reactor achieved initial criticality on July 27 and connected to the grid on August 8. Once commercial operation of the unit has begun, Tianwan will boast five operating reactors.

WNA: Nuclear generation in 2019 close to record high

August 26, 2020, 10:13AMNuclear News

Global nuclear power generation in 2019 totaled 2,657 TWh, second only to the 2,661 TWh generated in 2006, according to the World Nuclear Performance Report 2020, released yesterday by the World Nuclear Association. This is the seventh consecutive year that nuclear generation has increased, the WNA noted, with output 311 TWh higher than in 2012.

“In 2020, the world’s nuclear reactors have shown resilience and flexibility, adapting to changes in demand while ensuring stable and reliable electricity supplies,” said WNA Director General Agneta Rising.