Newswire

Tag: georgia power

Vogtle-3 fuel load has begun

October 14, 2022, 12:01PMNuclear News
Vogtle Unit 3 in September. (Photo: Georgia Power)

Georgia Power announced this morning that fuel loading at Vogtle-3 has commenced, marking an important milestone on what has proved to be a long and bumpy road to startup and commercial operation of the first new nuclear power reactors to be built in the United States in more than three decades. (Major work on the Vogtle-3 and -4 project began in 2012, with a price tag of $14 billion and scheduled unit start dates of 2016 and 2017. The project’s total cost is now expected to exceed $30 billion.)

Southern plans second license renewal for Hatch

September 2, 2022, 7:04AMNuclear News
The twin-unit Hatch plant (Image: Southern Nuclear)

Southern Nuclear, operator of the two-unit Hatch nuclear plant, announced yesterday that it will seek subsequent license renewals (SLR) for both reactors.

NRC okays fuel loading at new Vogtle unit

August 4, 2022, 9:30AMNuclear News
Unit 3 at the Vogtle site in July 2022. (Photo: Georgia Power)

The Nuclear Regulatory Commission has authorized Vogtle plant operator Southern Nuclear to load fuel and begin operation at Unit 3—the first reactor to reach this point in the agency’s combined license process. (Prior to 1989, reactors were licensed under a two-step process, requiring both a construction permit and an operating license.)

Georgia Power sued by Vogtle co-owners

June 24, 2022, 9:30AMNuclear News
Vogtle Units 3 and 4, with Units 1 and 2 in the background. (Photo: Georgia Power)

Both Oglethorpe Power Corporation and the Municipal Electric Authority of Georgia (MEAG), two co-owners of the Vogtle nuclear plant, have filed lawsuits against Southern Company subsidiary Georgia Power, the facility’s primary owner.

Oglethorpe and MEAG are 30 percent and 22.7 percent owners, respectively, of Vogtle. Georgia Power holds a 45.7 percent share. (Dalton Utilities, which owns 1.6 percent of the plant, is not involved in the suits.)

Vogtle project update: Cost likely to top $30 billion

May 9, 2022, 3:01PMANS Nuclear Cafe
The Vogtle-4 diesel generator building in March. (Photo: Georgia Power)

The total bill for the reactor expansion project at the Vogtle nuclear plant in Georgia is now expected to exceed $30 billion, according to the Associated Press. The original price tag for the two Westinghouse AP1000 units was $14 billion.

Vogtle project hit with new delay, higher cost

February 22, 2022, 9:30AMNuclear News
Fuel preparing to be unloaded outside of Vogtle-3 last month. (Photo: Georgia Power)

Commercial operation dates for the two new reactors under construction at the Vogtle nuclear plant have been pushed back yet again, adding to the project’s total cost, Southern Company announced last week. The Vogtle plant is near Waynesboro, Ga.

During its February 17 fourth-quarter earnings call, Southern reported that the projected start dates for both reactors were being extended by three to six months. Vogtle-3 is now expected to begin providing electricity to Georgians in the fourth quarter of 2022 or first quarter of 2023, with Vogtle-4 coming on line in the third or fourth quarter of 2023.

Vogtle’s Unit 3 in-service date on target for this year

January 31, 2022, 12:00PMANS Nuclear Cafe
In a photo from November 2021, the Vogtle plant’s Unit 4 is in the foreground, and Unit 3 is in the center. Units 1 and 2, which entered service in the 1980s, are shown at the top of the photo. (Photo: Georgia Power)

A spokesperson for Georgia Power has confirmed that the projected in-service date for the new Vogtle-3 reactor remains the third quarter of 2022, according to an article published on January 27 on the Power magazine website. The in-service date for Vogtle-4 is targeted for the second quarter of 2023, the spokesperson said.

Latest delay to Vogtle project may not be the last

December 8, 2021, 3:00PMNuclear News
Vogtle Units 3 (in foreground) and 4, in November. (Photo: Georgia Power)

Georgia Power has revised the projected commercial operation dates for Vogtle-3 and -4 a total of four times this year—most recently in October—but some experts are saying that at least one more delay is probable.

Georgia Power again pushes back Vogtle project start dates

October 25, 2021, 9:29AMNuclear News
Vogtle-4 containment as it appeared last month. Photo: Georgia Power

In what has become for nuclear advocates an all-too-familiar refrain, Georgia Power has made another revision to the Vogtle nuclear expansion project schedule. The company now predicts a Unit 3 in-service date in the third quarter of 2022 and a Unit 4 in-service date in the second quarter of 2023, representing a three-month shift for each unit.

NRC may step up scrutiny of Vogtle project

August 31, 2021, 9:30AMNuclear News
Vogtle-3 (left) and -4 in June. (Photo: Georgia Power)

Oversight of the Vogtle nuclear new-build project will be increased if the preliminary conclusions in an August 26 Nuclear Regulatory Commission special inspection report are finalized.

Conducted from June 21 to July 2, the inspection looked into the cause and extent of construction-quality issues in the safety-related electrical cable raceway system at Vogtle-3.

Vogtle project suffers another setback

July 30, 2021, 12:00PMNuclear News
Vogtle Units 3 and 4, earlier this month. (Photo: Georgia Power)

Georgia Power yesterday announced that due to 'productivity challenges' and the need for 'additional time for testing and quality assurance,' it has revised the schedule for the Vogtle-3 and -4 nuclear expansion project. The new schedule pushes back the Unit 3 in-service date to the second quarter of 2022 and the Unit 4 date to the first quarter of 2023—a three-to-four-month shift for each unit.

Experts predict further delay to commercial start of Vogtle-3

June 11, 2021, 7:02AMNuclear News
Vogtle-3’s containment (right) and turbine building (left) in May. Photo: Georgia Power

Georgia Power recently pushed back its projected commercial operation date for Vogtle-3 from December of this year to January 2022, but now some engineering and financial experts are saying that this revised date is too optimistic.

Vogtle-3 startup delayed until January as costs increase

May 20, 2021, 7:15AMNuclear News

The commercial start date for Unit 3 at the Vogtle construction site near Waynesboro, Ga., has been pushed back to January of next year, adding some $48 million to the cost of the nuclear new-build project, according to Georgia Power and Southern Nuclear officials who were testifying at a May 18 hearing before the Georgia Public Service Commission.

Southern targets December for Vogtle-3 startup

May 3, 2021, 6:54AMANS Nuclear Cafe
Vogtle-3 turbine generator. Photo: Georgia Power

Southern Company is targeting December for placing Vogtle-3 in service, according to Tom Fanning, the company’s chairman, president, and chief executive officer, who spoke with financial analysts on April 29 in its first-quarter earnings call. “The site work plan now targets fuel load in the third quarter and late December 2021 in-service date for Unit 3,” Fanning said. “Of course, any delays could result in a first-quarter 2022 Unit 3 in-service date.”

Latest from Vogtle: Unit 3 hot functional testing begins, Unit 4 water tank placed

April 27, 2021, 3:01PMNuclear News
The CB-20 module is placed atop the Vogtle-4 containment vessel. Photo: Georgia Power

Georgia Power yesterday announced two significant milestones at the Vogtle nuclear plant’s expansion project: the commencement of hot functional testing at Unit 3 and the placement of Unit 4’s passive containment cooling water storage tank, known as CB-20.

Vogtle-3 “likely” to miss scheduled start date, says Georgia Power

March 22, 2021, 3:02PMNuclear News

Vogtle-3's containment and turbine building. Photo: Georgia Power

Vogtle-3, the first of two 1,100-MWe AP1000 pressurized water reactors under construction at the Vogtle plant near Waynesboro, Ga., may not go into service in November as planned, Southern Company subsidiary Georgia Power has announced.

According to a March 19 filing with the Securities and Exchange Commission, the date for starting commercial operation at Unit 3 could be delayed by a month or more at a cost to Georgia Power of approximately $25 million per month. “While [Vogtle plant operator] Southern Nuclear continues to target a November 2021 in-service date for Unit 3, the schedule is challenged and … a delay is likely,” Georgia Power stated. The filing made no mention of changes to Unit 4’s scheduled start date of November 2022.

More adjustments to Vogtle milestone dates likely

January 13, 2021, 3:08PMNuclear News

The initial shipment of nuclear fuel for Unit 3 arrives at the Vogtle site in December. Photo: Georgia Power

Largely as a result of the continuing COVID-19 crisis, the Vogtle reactor-construction project team expects to further adjust dates for achieving key project milestones, including the start of hot functional testing and fuel load for Unit 3, Southern Company subsidiary Georgia Power announced on January 11.

The company added, however, that it continues to expect to bring Unit 3 into service this November and Unit 4 into service in November 2022. Additional updates on the project will be provided during Southern’s quarterly earnings call next month.

First fuel shipment for Vogtle-3 delivered

December 14, 2020, 9:35AMNuclear News

Southern Company subsidiary Georgia Power has announced the receipt of the initial shipment of nuclear fuel for Vogtle-3, characterizing the event as a “major step” for the two-unit nuclear expansion project currently under way at the Vogtle nuclear power plant near Waynesboro, Ga.

Next step: With the receipt of the first nuclear fuel assemblies, the project is now focused on one of the major milestones for Unit 3, hot functional testing, the last critical step before fuel load and, ultimately, in-service operation, Georgia Power said.

In October, Vogtle plant operator Southern Nuclear announced a readjustment of its July 2020 “aggressive site schedule” dates for Unit 3 hot functional testing, fuel load, and commercial operation. The dates were moved from October 2020, December 2020, and May 2021, respectively, to January 2021, April 2021, and the third quarter of 2021. Southern Nuclear said that hot functional testing could start as late as the end of March 2021 and fuel load as late as mid-year 2021 without jeopardizing Vogtle-3’s November 2021 regulatory approved in-service date.