Major concrete work completed on Savannah River disposal unit

June 13, 2024, 12:00PMRadwaste Solutions
All major concrete placements have been completed on Saltstone Disposal Unit 10, the latest megavolume disposal unit being built at the Savannah River Site. This aerial view shows the final roof section being installed on the unit. (Photo: DOE-EM)

With the placement of 25 wall sections, 208 support columns, and 7 roof sections, work crews have completed all major concrete placements for the megavolume Saltstone Disposal Unit (SDU) 10 at the Savannah River Site in South Carolina, according to the Department of Energy’s Office of Environmental Management.

Savannah River Site's one-of-a-kind transporter makes pit stop

May 30, 2024, 9:30AMRadwaste Solutions
The Savannah River Site’s shielded canister transporter. (Photo: DOE)

The large vehicle used to transport highly radioactive canisters at the Department of Energy’s Savannah River Site has completed a pit stop to ensure the continued movement of the site’s radioactive liquid waste work.

Savannah River contractor receives NSC safety awards

May 20, 2024, 9:33AMRadwaste Solutions
SRMC operators demonstrate procedure compliance during a job at the Savannah River Site’s Saltstone Production Facility. SRMC recently won national awards for demonstrating a commitment to working safely. (Photo: SRMC)

Department of Energy cleanup contractor Savannah River Mission Completion (SRMC) has garnered national recognition for its commitment to safety, recently receiving three awards from the National Safety Council: the Occupational Excellence Award, the Perfect Record Award, and the Superior Safety Performance Award.

Savannah River Site offers select interns a career fast track

January 3, 2024, 3:00PMNuclear News
While interning at SRS, Texas Tech senior Jinju Philip spent time in the quality assurance program inside the Defense Waste Processing Facility. He now works part time in the Technical Student Program as a system engineer for the site’s tank closure effort. (Photo: SRMC)

The Department of Energy Office of Environmental Management’s liquid waste contractor at the Savannah River Site is giving nine college students the opportunity to jump-start their careers this year through a hybrid work program that allows them to finish their engineering or computer science studies while also interning at SRS.

Technical college introduces nuclear apprenticeship program

November 6, 2023, 9:30AMNuclear News
SRMC’s Dave Olson makes opening remarks to the new class of nuclear operator apprentices and faculty members at Denmark Technical College. (Photo: SRMC)

Eight new hires from Savannah River Mission Completion (SRMC) are taking part in the new Liquid Waste Nuclear Operator apprenticeship class at Denmark Technical College in Denmark, S.C. The goal of the class is to prepare SRMC’s new employees for positions at the Department of Energy’s Savannah River Site, in South Carolina.

SRS employees use novel training exercise to align waste mission

October 5, 2023, 3:02PMRadwaste Solutions
Ray Tran, an engineer for Savannah River tank farms, helps complete a timeline of SRS historical events as part of SRMC’s vision casting training initiative. (Photo: DOE)

More than 3,000 employees with Department of Energy contractor Savannah River Mission Completion (SRMC) participated in a vision casting initiative, learning more about the past, present, and future of the Savannah River Site’s liquid waste mission.

DOE turns to junior colleges for cleanup workforce pipeline

March 10, 2023, 7:01AMRadwaste Solutions
Southeast New Mexico College staff visit the WIPP site. (Photo: WIPP)

Two Department of Energy sites recently announced training partnerships with local technical and community colleges designed to offer students hands-on work experience while building a workforce pipeline to waste management jobs.

Savannah River’s DWPF receives upgrades, exits outage

February 15, 2023, 9:40AMRadwaste Solutions
Savannah River’s DWPF has completed the conversion from formic acid to glycolic acid in the waste vitrification process. (Photo: DOE)

The Defense Waste Processing Facility (DWPF) at the Department of Energy’s Savannah River Site (SRS) in South Carolina has resumed operations after a completing a processing improvement that the DOE said will enable safer operations and more efficient vitrification of radioactive waste.

Subcontracts awarded in support of Savannah River’s liquid waste mission

August 31, 2022, 9:30AMRadwaste Solutions

Department of Energy contractor Savannah River Mission Completion (SRMC) announced it has awarded four subcontracts worth a total of approximately $20 million to perform key engineering support for the liquid radioactive waste mission at the department’s Savannah River Site near Aiken, S.C. Among the awardees are locally owned businesses and a woman-owned small business.

DOE prepares for construction of Savannah River’s final waste disposal units

August 18, 2022, 12:02PMRadwaste Solutions
Crews begin clearing the site on which Savannah River Site’s SDU 10 will sit. (Photo: DOE)

The Department of Energy’s Office of Environmental Management (EM) announced that it is preparing for construction of the final three planned saltstone disposal units (SDUs) at the Savannah River Site in South Carolina, which will complete the site’s liquid waste mission.

The SRS liquid waste contractor, Savannah River Mission Completion (SRMC), is overseeing the construction of the SDUs, which will receive decontaminated salt solution treated at Savannah River’s Salt Waste Processing Facility (SWPF).

DOE awards contracts for Oak Ridge, SRS work

October 29, 2021, 12:00PMRadwaste Solutions
The Defense Waste Processing Facility at the Savannah River Site in South Carolina. (Photo: DOE)

The Department of Energy’s Office of Environmental Management (EM) has awarded Savannah River Mission Completion (SRMC), of Lynchburg, Va., the Integrated Mission Completion Contract at the Savannah River Site near Aiken, S.C. The single-award, master indefinite delivery/indefinite quantity contract has an estimated contract ceiling of approximately $21 billion over a 10-year ordering period, with cost-reimbursement and fixed-price task orders to define the contract performance.