New welding school opens for high schoolers

November 20, 2024, 12:01PMANS Nuclear Cafe

With the support of a $500,000 grant from BWX Technologies (BWXT), the U.S. Navy, and BlueForge Alliance, the John D. Haynes School of Welding Technology has opened at Mount Vernon High School in Indiana. The welding school offers direct employment opportunities for students from the high school to BWXT’s Nuclear Operations Group, also located in Mount Vernon, Ind. Students can complete their high school degrees and their professional welding testing on a dual track, allowing them to enter the workforce immediately upon graduation.

ITER leaders outline plan for component repairs and replacements

January 11, 2023, 12:00PMNuclear News
The cooling pipes that snake along the surface of the vacuum vessel thermal shield will be removed and replaced. Here, on a right-hand outboard panel, workers determine the impact of pipe removal on the surface of the component. (Photo: ITER Organization)

ITER’s machine assembly phase began about two and a half years ago. Now, staff are reversing some of that assembly work to make needed repairs. According to a news article published by the ITER Organization on January 9, ITER is “facing challenges common to every industrial venture involving first-of-a-kind components.” Over one year after problems were first detected and less than two months after they were made public in late November, tests and analysis are producing a clearer picture of necessary repairs to the tokamak’s thermal shield panels and vacuum vessel sectors.

“There is no scandal here,” said ITER director general Pietro Barabaschi. “Such things happen. I've seen many issues of the kind, and much worse.”

Stress corrosion cracking and welding nonconformities are behind ITER’s fresh delays

December 5, 2022, 3:00PMNuclear News
A total of about 23 kilometers (about 14 miles) of piping are welded to the surface of the thermal shield panels. The piping on a vacuum vessel thermal shield panel is clearly visible in this photo. (Photo: ITER Organization)

The ITER Organization is working on a new baseline schedule for the magnetic confinement fusion experiment launched in 1985 and now under construction in southern France. First plasma was scheduled for December 2025 and deuterium-tritium operations for 2035 under a schedule approved in November 2016 that will soon be shelved. In addition to impacts from COVID-19 delays and uncertainty resulting from Russia’s war in Ukraine, ITER leaders must now factor in repair time for “component challenges.”

Holtec touts advances in welding, NDE technologies

November 1, 2021, 9:30AMANS Nuclear Cafe

Holtec International said its manufacturing specialists continue to bring forth new welding and weld examination technologies. The company recently highlighted three “landmark achievements” that are transforming its manufacturing program.

In addition to manufacturing spent nuclear fuel storage and transportation casks, Holtec provides products and services to the nuclear industry, including nondestructive examination of in-service reactor components. The company is also developing its own small modular reactor, the SMR-160.