Concept art of the six-module Carbon Free Power Project, to be sited at INL. (Image: NuScale)
CFPP LLC, the limited liability company established by Utah Associated Municipal Power Systems (UAMPS) in 2020 to bring its Carbon Free Power Project to fruition, has applied to the Nuclear Regulatory Commission for a limited work authorization (LWA) to permit certain early project construction activities prior to the issuance of a combined license (COL). In a July 31 news release, CFPP said that should its application be approved, early-scope construction on the small modular reactor project would likely begin in mid-2025.
Vogtle-3 (Photo: Georgia Power)
To the ears of the nuclear community, the news from Georgia Power this morning may sound a bit like “Ode to Joy” from Beethoven’s Ninth: After years of delay, Unit 3 at the Vogtle nuclear power plant has entered commercial operation, becoming the first newly constructed power reactor in the United States in more than 30 years and the nation’s first Westinghouse-supplied Generation III+ AP1000 unit to be placed into service. The new unit joins Vogtle-1 and -2—1,169-MWe four-loop pressurized water reactors that entered commercial operation in the late 1980s.
The Vogtle-4 control room. (Photo: Georgia Power)
The Nuclear Regulatory Commission has authorized Southern Nuclear Operating Company to begin loading fuel into Unit 4 at the Vogtle nuclear expansion site near Waynesboro, Ga., making the unit the second reactor to reach this milestone in the agency’s combined license process—a little less than one year after Vogtle-3. (Prior to 1989, reactors were licensed under a two-step process, requiring both a construction permit and an operating license.)
Vogtle’s Unit 4 reactor in June. (Photo: Georgia Power)
Southern Nuclear, operator of Georgia’s Vogtle plant, has informed the Nuclear Regulatory Commission that all 364 inspections, tests, and analyses for Unit 4 have been performed, and all acceptance criteria for the new reactor have been met. Primary plant owner Georgia Power made the announcement last Friday.
The Darlington nuclear power plant. (Photo: OPG)
Ontario Power Generation has achieved another milestone in its massive Darlington nuclear plant refurbishment project, and in rather impressive fashion: The Unit 3 CANDU reactor has been reconnected to Ontario’s electricity grid 169 days ahead of schedule, according to a July 18 OPG media release.
The Perry nuclear power plant. (Photo: ANS)
Energy Harbor has filed its initial license renewal application for the Perry nuclear power plant, requesting an additional 20 years of operation for the facility, the Nuclear Regulatory Commission announced yesterday. Dated July 3, the 2,427-page application is now available on the agency’s website.
From left: Petr Brzezina, president, Westinghouse Czech Republic and Slovakia; Elias Gedeon, senior vice president, Westinghouse commercial operations; Gautam Rana, U.S. ambassador to Slovakia; and Pavol Štuller, chairman of the board and chief executive officer, JAVYS. (Photo: Westinghouse)
Westinghouse Electric Company yesterday announced the signing of two memorandums of understanding with Slovakia’s state-owned nuclear company JAVYS regarding the potential deployment of the U.S. firm’s AP1000 reactors and AP300 small modular reactors.
In the foreground, from left: Ukrainian energy minister German Galushchenko and Bulgarian energy minister Rumen Radev at the MOU signing ceremony in Sofia, Bulgaria. Looking on are (from left) Ukrainian president Volodymyr Zelenskyy and Bulgarian prime minister Nikolai Denkov.
The energy ministries of Bulgaria and Ukraine have announced the signing of a memorandum of understanding to expand collaboration in the energy sector, including the nuclear energy sector.
Ontario energy minister Todd Smith (left) and Ontario Power Generation president and CEO Ken Hartwick announce plans for three more BWRX-300 units at Darlington. (Photo: OPG)
If we’re in a new nuclear renaissance, its capital would appear to be Ontario. On July 7, just two days after debuting a collaboration with Bruce Power to build up to 4.8 GW of new nuclear generation at the Bruce plant, the government of Ontario announced that it is working with Ontario Power Generation to begin planning and licensing for the deployment of three additional GE Hitachi Nuclear Energy (GEH) BWRX-300 small modular reactors at that utility’s Darlington site.